UP RERA withdrew its 2023 order in May and issued new guidelines. If a buyers' group or a government agency completes a project after the registration is cancelled, they're not liable for refunds awarded earlier against the original builder. Those refunds can still be chased against the builder, but not out of the project's assets.
The flip side: if you ask for a refund while completion work is going on, RERA may suggest deferring it, and even if it decides your case, the order stays on hold until the project is done.
Anyone in one of these projects? Does this change whether you stay in or try to exit?
Source: https://www.livelawbiz.com/rera/up-rera-issues-fresh-guidelines-for-stalled-projects-clarifies-refund-liability-542061