Tulsidal Tulsidham, Dombivli East - reviews and RERA status?

Started by Pankaj Joshi

Dombivli is one location where a RERA number on its own isn't enough verification, so worth being careful here.

On the project: Tulsidal Tulsidham, Dombivli East, by Tulsidal Builders and Developers, appears under MahaRERA registration P51700030926, registered 29 September 2021 with a proposed completion date of 31 December 2025. Listed at 51 units.

The first thing that stands out is that the proposed completion date has now passed by around nine months. So pull these up on maharera.maharashtra.gov.in against that registration number: whether an extension was applied for and granted and what the revised date is; current registration status (valid, extended or lapsed); and the quarterly progress filings, which show units booked against total and approvals taken versus pending. Those filings are the promoter's own submission to the regulator and often read very differently from a site visit.

Now the Dombivli-specific part, which matters. A KDMC inquiry following a PIL in the Bombay High Court found that 65 builders had obtained MahaRERA certificates using forged and fabricated municipal documents, without holding valid building permissions. The High Court ordered demolition of those buildings, affecting roughly 6,500 homebuyers, and a Thane police SIT has made arrests including developers and document forgers.

To be clear, I'm not suggesting anything about this particular project — I have no information either way. The point is structural: in Dombivli the fraud ran through RERA registration itself, so a valid-looking RERA certificate does not by itself confirm municipal approvals exist.

So verify the KDMC side independently. Ask for the commencement certificate and sanctioned plan, then confirm them directly with KDMC rather than relying on copies from the builder. If it's being sold as near-complete, ask where the occupancy certificate application stands.

What stage is construction at, and have you been given CC and sanctioned plan copies yet?

Replies (2)

Pooja Chatterjee

Following up on the Dombivli point, because two details have surfaced that sharpen it considerably. First: regularisation was attempted and it failed. KDMC told the High Court in February that it had received regularisation applications for 38 of the 65 buildings, and every one was rejected for not

Harsh Desai

Picking up the 2026 gap you flagged. I couldn't find anything from this year either, but there's a June 2025 ruling that answers the question underneath it. The Bombay High Court refused relief to one of these buildings and held plainly that registration under RERA does not legalise unauthorised con