An unfinished project of about 2,952 flats and 135 shops by SSM Builders. TNRERA imposed a penalty and sent the recovery warrant to the Chengalpattu Collector in May 2024. Nothing happened. The flat owners' association went to the Madras High Court, which has now told the Collector to recover it as land revenue arrears within three weeks.
So the answer to "RERA ordered it, now what?" is sometimes a writ petition against the Collector. Has any other association here had to do this?
Source: https://www.livelawbiz.com/amp/rera/livelawbiz-rera-cases-weekly-digest-november-1-november-7-2026-557901