Three years from the promised date, not from when you got the keys. TN tribunal on RERA compensation claims

Started by Monika Das

A villa owners' association against Bahri Estates. The appellate tribunal dismissed it on limitation: a compensation claim for breach of the agreement has to be filed within three years, and the clock starts on the agreed completion date. Getting possession late doesn't restart it.

That catches a lot of people who wait for the keys before complaining. Anyone here been told their claim was too late?

Source: https://www.livelawbiz.com/rera/livelawbiz-rera-weekly-digest-october-19-october-24-2026-555952

Replies (1)

Riya Nayak

A notice from you doesn't stop the clock. A written acknowledgment from the builder can, under section 18 of the Limitation Act, so keep any letter or email where they admit the delay.