The Supreme Court said it might be "better to abolish" RERA. Worth reading what it actually criticised.

Started by Vijay Goswami

In February the Supreme Court remarked that if RERA only shields errant developers and fails to protect buyers, it might be better to abolish this institution. No order followed and it was an observation during hearing rather than a ruling. But the specific criticisms describe what a lot of people here have lived through.

Three points from the bench stand out.

That RERA has become a rehabilitation centre for retired officers. That's a point about who staffs these authorities, and whether that composition produces regulators willing to move against developers.

That a sixty-day statute has delivered five-year litigation. The Act contemplates rapid disposal. In practice cases run for years, and in several states recovery certificates sit unenforced long after the allottee has won.

And that mandatory registration has been reduced to a dead letter. MahaRERA alone has flagged more than 10,700 lapsed projects, with Pune accounting for around 3,400.

The Prime Minister made a related point at a Pragati review in May, pressing authorities to stop reporting complaint-closure counts and start showing whether buyers actually received relief. Those are different metrics, and the gap between them is most of the problem.

In fairness, the machinery does work. This month the Supreme Court directed Vatika to deposit over Rs 1 crore for four Gurugram buyers over delayed possession. It works — just slowly and unevenly.

The practical conclusion I'd draw, and I'd welcome disagreement: if the regulator takes years, pre-purchase verification is worth far more than post-purchase remedy. Checking a promoter's quarterly filings and past extension record costs an afternoon. Winning at RERA and then waiting to enforce costs years.

Replies (1)

Bhavna Mehta

On what would actually fix it — a large part of the failure isn't inside RERA at all, which is why abolishing it wouldn't help. Look at where an order dies. The Authority hears the case and issues a recovery certificate under Section 40(1). But realisation of that money as arrears of land revenue is