Surat: builder got the project deregistered, GujRERA still ordered refunds

Started by Rajesh Trivedi

Tulsi Patra Residency's developer had the project's RERA registration cancelled in 2021. Seven shop buyers, who had paid between Rs 22 lakh and Rs 42 lakh, complained anyway. This April GujRERA said deregistration doesn't take away its power: the buyers are allottees, and it ordered their money back with 9% interest. It also opened its own case into what was disclosed when the registration was cancelled.

Worth knowing if a builder tells you "the project is no longer under RERA". Has anyone been told that?

Source: https://deshgujarat.com/2026/04/20/gujrera-directs-refund-with-interest-to-buyers-in-de-registered-surat-project/

Replies (1)

Ajay Walia

Also worth knowing: section 8 of the Act covers what happens after a registration lapses or is revoked. The authority can have the remaining work done, including by the allottees' association. Deregistration isn't meant to be an exit door.