Three flats in Sportsville were due on 31 December 2025. The buyers say the promoter shifted that to 1 April 2026 without their consent. There was still no OC when MahaRERA decided the case on 23 July. It ordered interest from 1 January 2026 until possession with OC.
The promoter had applied for the OC in mid-December. That didn't count either.
Has your builder sent a "revised possession date" letter? Did you reply to it in writing?