Penthouse in Godrej Meridien-II. The builder had an occupation certificate and offered possession, but the penthouse wasn't habitable. The authority listed three conditions for a valid offer: OC first, a unit you can live in, and no unreasonable extra demands. It ordered delay interest at 10.80%.
So an "offer of possession" letter doesn't stop the delay interest by itself. Did yours come before the flat was finished?
Source: https://www.livelawbiz.com/rera/livelawbiz-rera-weekly-digest-october-26-october-31-2026-556847