New Chandigarh: no delay clause in the agreement, Punjab RERA gave interest anyway

Started by Ashish Jain

A couple had paid Rs 61 lakh for a flat promised by December 2022. The builder then sent a fresh demand of over Rs 26 lakh, with no occupation certificate and no delay compensation. It argued arbitration and that the buyers had defaulted. Punjab RERA rejected both and said the right to delay interest doesn't disappear just because the agreement left it out.

Has anyone got a fresh demand letter without an OC attached? Did you pay it?

Source: https://www.outlookmoney.com/invest/contract-terms-cannot-defeat-buyers-rights-punjab-rera