New builder took over your stalled project. Does it owe you for the old builder's delay?

Started by Falak Sharma

Two rulings within days of each other, and they don't point the same way.

Maharashtra's appellate tribunal, in a Nirmal Lifestyle matter: a builder that takes over under section 15 inherits the earlier builder's delay interest. Consent letters signed by most buyers don't bind the ones who refused.

Bombay High Court, 5 November: an incoming developer isn't liable for the previous developer's refund dues just because it knew about them. There has to be a contract or a statute behind it.

So it seems to turn on how the new builder came in. If your project changed hands, what did your papers say about old dues?

Source: https://www.livelawbiz.com/rera/livelawbiz-rera-cases-weekly-digest-9-november-14-november-2026-558629

Replies (1)

Rashmi Gandhi

Also check how the transfer was done. Section 15 needs prior written consent from two-thirds of the allottees and the authority's approval. If nobody asked you, that's worth raising.