A buyer's account went widely shared this week — purchased in 2023 on a mid-2026 possession commitment, then pressed for three months by the developer's CRM team to sign a consent form modifying the RERA registration, so that eight to nine additional floors could be added without adding any land to the project. Full EMI being paid, construction reportedly stalled, RERA date now said to be 2028.
Those are one buyer's allegations and unverified. The mechanism underneath is worth understanding regardless, because it explains why the pressure exists and shows where the leverage actually sits.
Under Section 14(2)(ii) of RERA, a promoter cannot make alterations or additions to the sanctioned plans, layout plans, or specifications of the building or common areas without the prior written consent of at least two-thirds of the allottees, excluding the promoter. That applies notwithstanding anything in any contract or agreement.
That two-thirds threshold is the entire reason consent campaigns exist. Your signature isn't paperwork, it's the statutory gate. Which also means an organised group holding more than one-third can block the modification outright.
Three things worth knowing before signing anything.
Consent, once given in writing, binds you. A RERA authority has held that allottees are estopped from withdrawing written consent given under Section 14. There is no cooling-off period.
Silence may not protect you. In one Karnataka appellate ruling, authenticated emails were accepted as valid consent and buyers who did not respond were treated as not objecting. So if you object, object in writing, on record, with proof of delivery. Ignoring the calls is the worst available option.
Check what else the document does. If a plan-modification consent also revises the possession date, you may be signing away accrued delay compensation under Section 18 alongside the plan change. Those are separate matters and should stay separate.