Flat registered but no OC. How are people in Bangalore getting power and water now?

Started by Ishan Chawla

Since the Supreme Court's order in December 2024, electricity and water connections aren't supposed to be given to a building without an occupancy certificate. Plenty of small apartment blocks in Bangalore never got one.

If you bought in a building like that: are you on a temporary connection, the builder's meter, tankers? And is there any sign of the OC coming?

Replies (1)

Bhumi Joshi

Ask the builder for the OC application number and where it's stuck. If it's waiting on a fire NOC, it can come. If the building has setback or floor deviations, it may never come, and that's a very different situation.