A buyer in Kumar Properties' 47 East was due possession on 28 March 2025. The developer said it handed over the flat in June 2025 for interior work. The part OC only came on 27 March 2026.
MahaRERA ordered delay interest in April, and on 9 July threw out the developer's review plea.
Has anyone here been asked to take keys "for interiors" before the OC? Did you sign anything saying possession was taken?