Antriksh Developers appealed against a UP tribunal order. The High Court dismissed it: an allottee who stays in the project can claim interest for every month of delay, section 18(1) sets no limitation for that, and the word "demand" in the proviso doesn't take the right away.
So "you didn't ask earlier" isn't a defence for the months you waited. Has your builder tried that one?