Builder-buyer agreements still have asymmetric penalty clauses — RERA hasn't fixed this

Started by Jagdish Prasad

RERA mandated a lot of important buyer protections — project registration, escrow, timelines, and grievance redressal. But one area where it fell short is the builder-buyer agreement itself.

The standard BBA in most states still contains clauses where: - Buyer default (delayed EMI, cancellation) attracts 10–15% forfeiture of the total consideration - Builder delay attracts interest at SBI PLR or 2% per annum on the amount paid — which at current rates is roughly 8–10%

The asymmetry is stark. A buyer who defaults even briefly can lose 10–15% of their total investment. A builder who delays by 2–3 years pays interest that works out to a fraction of that — and often argues force majeure.

MahaRERA has started pushing model agreements and has flagged several unfair clauses. UP RERA has been more active in consumer-side orders. But the base BBA template in many states hasn't been standardised.

What would actually help: - A central RERA model BBA template with symmetric penalty clauses (builder delay = same % penalty as buyer default) - Mandatory disclosure of all deviations from the model BBA at time of registration - Auto-refund triggers at RERA level if builder delay crosses a defined threshold

Is anyone tracking which states have moved toward model agreements? Karnataka and Tamil Nadu have been quieter on this compared to Maharashtra.

Replies (3)

Pooja Chatterjee

this is such a common frustration and you're right that RERA hasn't really solved it structurally. the standard BBA most builders use still has the classic asymmetry - builder delays attract maybe 5-6 rupees per sqft per month as compensation, while buyer payment delays attract 18-24% interest per a

Bhavna Mehta

the rate disparity is the most obvious problem - builder charges 18-24% on delayed payments from buyer, but offers 2% per annum (SBI PLR linked as per RERA) as compensation for delays on their side. on a 1 crore flat delayed by 2 years, that's 4 lakhs as compensation while the same buyer would owe 3

Anand Bajaj

A TGRERA interim order from 30 October is worth adding, because it goes to the leverage rather than the clause, and that's the part this thread hasn't touched. A buyer complained that she signed with Pacifica Constructions Pvt Ltd in May 2018 for a flat at Bachupally. Agreed amount excluding taxes w