An older one but worth knowing for anyone stuck on Tonk Road. A flat in a Modest Infra project at Shivdaspura was booked in 2012, agreement in 2016, delivery promised by April 2021. The builder said it was 92% built and had SWAMIH funding. Rajasthan RERA noted the registration had lapsed and ordered the whole Rs 20.58 lakh back, with 11.10% interest counted from each instalment's date.
"92% complete" didn't save the builder. Is anyone here still waiting on a project that's been "almost done" for years?
Source: https://www.pinkcitypost.com/rera-orders-refund-to-buyer-after-13-year-delay-in-housing-project-in-jaipurs-shivdaspura/