Bihar RERA missed its 30-day deadline, so the project counts as registered

Started by Charu Kapoor

Patna High Court: RERA has 30 days to decide a registration application. Bihar RERA didn't, and kept asking for documents that aren't in the Act or the state rules. The court held the project deemed registered and said the authority can't demand papers beyond the prescribed list.

Good for builders stuck in the queue. For buyers it means a "registered" project in Bihar may never have been looked at properly. How do you check which kind you're buying into?

Source: https://www.livelawbiz.com/amp/rera/livelawbiz-rera-cases-weekly-digest-november-1-november-7-2026-557901

Replies (1)

Prachi Bhatia

That's straight from section 5(2) of the Act: if the authority doesn't decide in 30 days the project is deemed registered, and it has to issue the registration number within seven days after that.