AP RERA has extended every project timeline in the state by four months, automatically. What does that do to your delay compensation?

Started by Farhan Mishra

AP RERA has issued a blanket four-month extension to project timelines, and the mechanism is worth reading closely if you're waiting on possession in Andhra Pradesh.

Circular P/Extension/10/2026, dated 12 August 2026, follows a MoHUA advisory of 31 July. Acting under Sections 6 and 37 of the RERA Act, APRERA has ordered that registration and project completion timelines for all registered projects in the state whose original, revised or extended completion date falls on or after 28 February 2026 stand extended by four months. Projects registered on or after 1 August 2026 are excluded.

Two features stand out.

It is automatic. Promoters don't have to apply, don't have to demonstrate their specific project was affected, and pay no fee for the period. Every qualifying project gets it.

And the Force Majeure trigger is the West Asia situation, treated as a "war" for invoking the clause. The causal link to any individual Andhra project isn't established case by case, it's applied categorically.

The question I'd want answered clearly is what this does to delay compensation. Section 18 entitles an allottee to interest for delayed possession, calculated from the committed date. Clause (c) of the circular says the extension does not affect allottees' rights in respect of matters "unrelated to the delay covered by this Order" — which reads as though, for the delay that is covered, something may change. Whether four months of Section 18 interest simply vanishes for buyers isn't spelled out.

Worth separating two dates too. Your builder-buyer agreement carries its own possession date. The RERA registration timeline is a different instrument. Extending the latter doesn't obviously rewrite the former, and that distinction could matter before the Authority.

Anyone in an affected AP project — has your builder communicated a revised date, or did you have to find the circular yourself?

Replies (1)

Pankaj Joshi

Partial answer to the compensation question, and the position looks better than the circular's drafting suggests. The key distinction is between Section 6 and your agreement. Section 6 governs extension of project registration. There is no provision in the Act extending the possession timeline a pro